|
Harbor Tunnels |
|
Photos/Jack
Orton Miners and Milwaukee Metropolitan
Sewerage District workers are lowered into the joining of two
17-foot-diameter tunnels for sewer pipes this week near the
|
|
"Fire in the hole," yells MMSD senior
project manager Larry Ellis (left) as Paul Nolan sets off dynamite to
blast through a tunnel. |
|
About 250 feet underground, crews
inspect progress of one of the tunnels this week in the harbor siphons
project intended to reduce sewer overflows into Lake Michigan.
|
|
Graphic/David
Arbanas |
|
Breaking
Ground |
|
One tunnel will extend 2,050
feet north from |
As musicians pounded rhythms and
rocked the stages of Summerfest during the past nine days, construction crews
255 feet below the
There is no
precise tempo to the six daily underground blasts, three in each
tunnel.
Before each
one, a machine drills 80 holes precisely 10 feet, 6 inches into the rock face.
Several footlong sticks of dynamite are packed into the 2 1/2 -inch-wide holes
with long rods, then workers are evacuated by stepping into a steel cage. A
crane lifts the cage out of an access shaft.
An air horn
at the surface sounds one long sustained note when all are clear. Blasting caps
start the multiple explosions, and workers waiting on the rim of the shaft feel
"See if the
Big Gig can compete with that," Chuck Kennedy said this weekas he walked away
from the shaft to return to a nearby trailer office. Kennedy is a resident
engineer with consulting company Earth Tech Inc. and supervises daily
activities.
The
Milwaukee Metropolitan Sewerage District hired a joint venture of JF Shea
Construction Inc. and the Kenney Construction Co. to create the two tunnels as
part of a $138 million harbor siphons project intended to reduce sewer overflows
into
One tunnel
will extend 2,050 feet north from
By Friday
morning, blasting had pushed the north tunnel 870 feet and the west tunnel had
progressed 920 feet, Ellis said. Before tunneling could begin, workers first
excavated a vertical shaft from the surface of
A cluster
of pipes, or siphons, placed in each tunnel will carry sewage and storm water
collected by several large regional sewers directly to the
The siphons
will reduce the risk of sewer overflows in two ways: pushing more wastewater to
the plant and saving space in the deep tunnel storage system for wastewater from
other areas, said Mike Martin, director of technical services for the sewerage
district.
In 2002, a
state Legislative Audit Bureau evaluation of sewer overflows criticized a
bottleneck that occurs during storms: existing siphons could deliver only up to
260 million gallons of wastewater a day to the plant, though its treatment
capacity is 330 million gallons a day. That resulted in as much as 70 million
gallons a day of wastewater unnecessarily going into the deep tunnel during
heavy rains. When the underground storage caverns reach their capacity, sewers
overflow.
In a year's
time, the lack of siphon capacity results in an estimated 1 billion to 2 billion
gallons of wastewater being diverted to the deep tunnel that could have been
treated immediately, according to the audit. Wastewater reaches the
The
additional siphons, rehabilitation of regional collection sewers that connect to
the siphons and the construction of a 2 1/2 -mile-long wet weather relief sewer
beneath
On Monday,
the sewerage district's governing commission will be asked to award a $34
million contract to Michels Corp. for construction of the
The new
harbor siphons could be operating by summer 2009.
In creating
the 17-foot-diameter tunnels for the siphons, crews blast 10 feet of rock at a
time. Monitors on the surface measure ground vibrations throughout the
construction area.
Each
explosion yields about 160 cubic yards of shards, said Darrell Vliegenthart of
JF Shea, the project's general superintendent.
Crews must
wait about 30 minutes after a blast for the smoke and dust to clear before
returning to the tunnels. Rock is scooped up and taken to the access shaft,
where it is dumped into a steel bowl capable of carrying up to 13 cubic yards to
the surface.
A crane
operator tips the bowl and spills the rock fragments onto the ground. A
bulldozer carries the shards to the site of a former car ferry dock on the west
The rock
gradually will fill 2 1/2 acres of open water where the dock had been. This
landfill will be turned over to the